Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,456,613
Community Members
 
Community Events
176
Community Groups

Target Start and Target End Date do not exist in JIRA

Hi everyone,

I have a few questions about Portfolio Plug in and any help will be greatly appreciated as I am very confused to use this plug in for our project or not:

1. I have successfully imported my items from excel into jira and I have created a custom filed for start date. Therefore I have start date and end date for each stories and epics. But when I create a plan with these stories and epics the start and end date does not reflect on the schedule. I have noticed that there is a filed target start and target end that dictate the timelines but the only way to modify it is within the portfolio and not from the imported items. Currently when I import anything all the start date and end date is the same as the sprint start and end date. 

 

Is there a way to import items with their start and end date and if there is which fields there should be map to? This is very crucial to me as I need to bulk import information form a Microsoft project plan and I should be able to identify the start and end date. 

2. How can I color epics and stories? Based on which filter? I have noticed that it is possible with a theme but we do not have theme in Jira either as a field, so is this another manual configuration to have color based schedules or can be a filed while we are importing the information?

3. Last but not least, is anyone here who transferred a Microsoft project plan into Jira Portfolio?

Kind regards, 

Narges

 

 

 

 