Percentage of a project done does not equal the number of tasks completed

Valerie Boudreau July 12, 2021

The green/blue status bar says 20% complete because 2 of my 10 subtasks are complete, but my parent task is only 4% complete timewise. Timewise is what matters. Who cares if I have 49 tasks of 50 complete if the 49 complete tasks are 1 hour each and the uncompleted task is 2,000 hours. So I have 49 hours out of 2,050 hours, or 2.4% done. But JIRA tells me I'm 98% done. 

I'm highly surprised JIRA has been around so long and hasn't resolved this silliness. 