andrew.edwards August 11, 2021

Hi,

I'm using roadmap feature in a classic cloud JIRA project.

The EPICS are showing the schedule bar as shown in colour red but not the tasks.  All have start and due dates inserted.

Is this expected behaviour ?

 

Screenshot 2021-08-11 165940.jpg

 

6 comments

Comment

Log in or Sign up to comment
Jacob Vu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 23, 2021

Hi @andrew.edwards

Are you asking if it's normal for the Epic colour bar to be red but not the task bar? If so, this could be due to the way that you have the colouring set up. You can change it by "View settings" -> "Colour By" and configure it to what you'd like.

Hope that helps.

Jacob @ NorthTEK Consulting

Mik_P October 18, 2021

My menu of "View settings" has no "Colour by" chapter.

Screenshot 2021-10-19 at 09.56.30.png

Mik_P October 18, 2021

I see no answers for several months. It is sad.

Mik_P October 18, 2021

Andrew asked - is expected for the tasks in an epic to not be visible on a timeline, whereas the start and due dates were inserted?
I have the same question.
I suppose it is a bug.

Expected: The tasks are visible on a timeline.

Actual: Tasks are not visible on the timeline, only epics are.

Could anybody help to fix the issue?

Mik_P October 19, 2021

Seems I have found more. It is not an explanation of the failure. 

It is ridiculous, but Jira has this limitation.

Screenshot 2021-10-19 at 10.10.24.png

I would be happy to hear I the limitation could be avoided. 

Like # people like this
Kanatbek September 20, 2022

Is this limitation still active?

Nagyné Széles October 27, 2022

We experience the same, very uncomfortable. And not even logical, as roadmaps are even more needed in non-agile projects.

Brian Candiloro November 4, 2022

Having the same issue.  We have our tasks in a scrum board, but this still does not work.  Is a scrum team different than a scrum board, if so, how does one configure a scrum team?

Jeff Newswanger December 28, 2022

I ran into this very thing.  I do not have sprints/scrum initiated but use backlog and roadmap.

image.png

I found if I go to project settings>Board>Roadmap there is a toggle for Child Level Issue Scheduling.  This allowed me to see the start and end date on the road map for issues other than epic.image.png

You must have start and due date on the child issue. Top bar is epic, bottom bar is child issue.

image.png

Like # people like this
Monique Burke
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 4, 2024

Thanks @Jeff Newswanger just the info I needed! 

Jeffrey Lapointe July 4, 2023

Thanks Jeff - Very helpful and worked like a charm

TAGS
AUG Leaders

Atlassian Community Events