Automatic movement of dependent tasks on timeline

Anne
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 2, 2022

Is there an option to make dependent (blocked) tasks move on the timeline, if i move a task that blocks it?

For example: A blocks B. A is moved on the timeline by two weeks. So B should move on the timeline by two weeks, too.

1 answer

1 accepted

0 votes
Answer accepted
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 2, 2022

Hi Anne-Sophie - Welcome to the Atlassian Community!

No, I don't think the dependent linked task will also move because it is not assumed that the timing is the same, just that they are dependent. But you might could do this with automation - changing the Start Date (or Due Date) of one issue if the linked issue Due Date changes. 

Raimund Antonitsch January 30, 2023

Hello @John Funk 

Thanks for this idea. How to implement this kind of automation. Sorry, but I'm new to JIRA automation. Thanks in advance

Like John Funk likes this
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 30, 2023

Hi Raimund - Welcome to the Atlassian Community!

It's better to open a new question, then more people can help with it. 

Like Anna Mohr likes this
TomT June 30, 2023

Hi Raimund,

 

I am looking to the same as you. Have you found out how to make this automation?

Like Rituporna De likes this