This is the view on Rally software, and the later image is from JIRA. I would like to view the tasks grouped by stories as in Rally, and not just as a list of tasks. Please let me know the configuration to be done. Thanks in advance.
Rally View
JIRA View
Though I have added a new column, I did not map the statuses
Please see "3) Create a new column and map it to the new Status" here:
https://confluence.atlassian.com/display/AGILE/Tutorial+-+Adding+a+Column+to+a+Board
Seems like what you're looking for is swimlanes based on Stories. To set them up, go to Board > Configure > Swimlanes and pick "Stories" from the dropdown. Note that this will work only if you use sub-tasks in your stories; from the screenshot you've provided, I can't tell if that's the case.