tempo timesheet - plan time - how to automatic span estimated time across days

Fabio Support May 22, 2014

As an user/administrator, how can I plan issues in order to have etimated time spanned automatically across available days?

CASE:

one issue is estimated 20 hours long.

the user wish to dedicate 2 hours a day

he would like to set a start day (or a range of days) and, given a time availability of at least 2 hours a day, have Tempo Timesheet span the issue estimated time along the available days.

In the example above, assuming to start on 1st of june, 2 hours a day, 20 hours estimate, means an elapsed of 10 days (1 to 12 of june with week end off).

CURRENT:

given the above example, if Tempo plan feature is choosen, no way to perform such task.

Even choosing range, the span is given moltiplicating 2 hours for the number of days in the range, regardless of the etimation.

In the example, if I choose a range from 1 to 20 of june, it moltiplicates 2 x 15 days (20 days with weekends off), 30 hours planned against the real and wished 20, overlocking by 1/3 the real availability.

1 answer

0 votes
Viðar Svansson [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 10, 2014

Hi Fabio, you are correct, Tempo does not offer functionality for this excact use case. We are very much aware of it however and hope to offer a better solution in the near future.