sprint completion

Hello everyone.
How to make sure that all the tasks in the status "testing" and has resolution, did not move to the next sprint or a backlog, and complete?

1 answer

This widget could not be displayed.

Hi Nikita,

Basically, when you close a sprint, all the issues that are not in the last column will be moved back to the next sprint or backlog. In this case, please make sure the status "testing" is mapped to the last column of your board.

Please see Configuring Columns for more details about it.

Cheers,

Clarissa.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,501 views 10 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you