can you tell me, if that is possible to change the two fields from one version, StartDate and EndDate, with the REST API?

1 answer

REST allows to update version's End Date (release date), but Start Date is not stored along with the standard Jira Version.

Therefore it is impossible to change Start Date with REST in version Jira 4.2.4

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 29, 2019 in Jira Software

Transforming Jira Software projects for general project management purposes

...It's true that there are projects in Jira; but they are merely a way to cut off issues, to tell them apart from other sections of work and to apply rules that are specific to that team (the schemes)....

206 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you