Account we are managing the Detailed Project Plan in Jira Advanced Roadmap.
We need a quick and easy way to raise flags coming out of the plan.
We are using
- Target End -Task Planned End Date
- Due Date- Task Realistic End Date populated by the team
- Original Estimate for task Effort and Time Remaining to calculate progress
We need a View/ Highlight is some way for the following:
- Items Due Date/Target End is in the coming 2 weeks
- Target End Past Due
- Due Date later then Target End
- Child Due Date/ Target End later then Parent Target End
- Parent has children with Any issue
I know the plan already shows alerts on
- Due Date past due with Status incomplete
- Parent with any Alter on Child level
- Child with Start Date earlier then Parent Start Date
- There are probably more I missed-?
Thanks.