if we use story points for estimation is there any way to get burndown prior to a story being resolv

Aimee Palmer June 15, 2017

we have a custom workflow that has in progress, QA, ready to release and Done.  i want ready to release to show as burndown on our chart.

1 answer

0 votes
Tarun Sapra
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 16, 2017

Hello Aimee,

On the scrum boards burndown is taken into account when the issue moves into the "right-most" column of the board, thus if you put the "ready to release" as the right most column then it will account for the burndown.

And once you have the burndown, you can bulk update the issues to "done" with resolution.

Aimee Palmer June 16, 2017

awesome! i will try it!  thank you

Aimee Palmer June 16, 2017

one more question...epics seem to be treated like any other issue vs a direct hierarchy.  while issues are grouped under an epic, when you start progress on an epic it lands on a board.  just wondering if i should even bother to put them through workflow?  thanks!