cannot complete sprint

Paul Glock December 5, 2017

I am new to JIRA so this is probably a pretty easy issue to resolve :)

I have setup a new Workflow and attached it to a Sprint Board. The final column is a DONE column. When I push the work into the DONE pile and complete the sprint it wants me to push all the done items back into the BACKLOG

I have used the Resolve Issue Screen in my transition as I thought this was causing the problem but which it puts a cross through the items it still does not allow me to close the sprint with these items complete.

 

error.png

 

 

2 answers

1 accepted

2 votes
Answer accepted
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 5, 2017

Hi Paul

The right hand column needs to be your Done column - I'm not sure why you want the Done column appearing before In Progress etc. Drag-and-drop the Done column in Board settings and it should work

Paul Glock December 5, 2017

Wow that was simple thanks Warren. I have always worked right to left so have setup the workflow to reflect the current non JIRA board. Not a problem to reverse :)

0 votes
Paul Glock December 5, 2017

ignore

Suggest an answer