analysis

Konstantin November 26, 2020

how can i check the number of issues in the backlog in previous sprints

1 answer

0 votes
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 27, 2020

Hello @Konstantin,

Thank you for reaching out to Atlassian Community!

On next-gen and classic software projects, there are reports where we can see incompleted issues of a completed sprint. 

The incompleted issues are the ones moved back to the backlog or moved to a new sprint.

For classic, the report is called Sprint Report and for next-gen, Sprint burndown chart. 

If that's not what you meant, please let us know more details about what you need so we can check here. 

Regards,
Angélica