Why the "plan mode" in Rapid Board is disabled?

Erez Efrati May 28, 2012

Per the documentation I have imported from our project from Pivotal Tracker.

Looking at the created Rapid Board the "Plan mode" is disabled for some reason.

Why is that?

2 answers

0 votes
DJ July 16, 2012

What year was this answered? No idea.

0 votes
Bastiaan Jansen
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 29, 2012

I would like to to point to the following link: https://answers.atlassian.com/questions/42257/how-to-use-scrum-with-greenhopper-rapid-board-why-is-the-scrum-option-disabled-on-rapid-board-from-which-version-of-greenhopper-do-we-have-scrum-option-for-rapidboard

To sum it up for you:

The plan option is only available when you use a scrum rapidboard. In order to enable the option from scrum rapidboards you will need to enable the "Greenhopper Labs" feature as explained in the other post.