Why doesn't the version report consider remaining estimate in calculating burn up?

I'm trying to use the Jira Agile version report to track progress to our version end date, but it's only considering completed work based on the original estimates for completed issues. We have stories that are partially complete, but it isn't taking the remaining estimates into account to estimate for the predicted end date. This is skewing the results -- seems like a bug? Any options to get the right calculation?

1 answer

I have the same question -- the estimate for our version report is off by months because it's using the original estimate, and not the remaining work. Help! We are looking to purchase this product, and this is a required feature for us.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

424 views 1 14
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot