Why doesn't the version report consider remaining estimate in calculating burn up?

I'm trying to use the Jira Agile version report to track progress to our version end date, but it's only considering completed work based on the original estimates for completed issues. We have stories that are partially complete, but it isn't taking the remaining estimates into account to estimate for the predicted end date. This is skewing the results -- seems like a bug? Any options to get the right calculation?

1 answer

I have the same question -- the estimate for our version report is off by months because it's using the original estimate, and not the remaining work. Help! We are looking to purchase this product, and this is a required feature for us.

Suggest an answer

Log in or Sign up to answer
Community showcase
Asked Thursday in Jira Ops

I'm John Allspaw, Ask Me Anything about incident analysis and postmortems

I'm John Allspaw, co-founder of   Adaptive Capacity Labs, where we help teams use their incidents to learn and improve. We bring research-driven methods and approaches to drive effective inciden...

5,052 views 20 14
View question

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you