Why do portfolio scope schedule view show sprint end date as end date for all issues in the sprint?

When we create a plan, sourced from scrum boards, the issues that are imported on the plan shows the end date as sprint end date. The schedule report view do not show the actual end date when the issue (story/sub-task) will finish. Please note, we are using person days for estimates (and not story points). So why can't Portfolio show the schedule with exact end date when the story/sub-task will finish based on the original/remaining estimates?

Please find below screenshot -

Portfolio schedule view.png

2 answers

Hello,

 

The reason for this is that your Portfolio team is set to Scrum mode. As a consequence, issues can only be finished at the end of a sprint. There is no rule when an issue has to be implemented during a sprint, thus it is theoretically possible that all issues get done not before the last day of a sprint.

 

In Kanban mode, issues can be finished daily. Change your team to Kanban and Portfolio will calculate the exact end date. 

 

Best regards,
Kevin

Suggest an answer

Log in or Join to answer
Community showcase
Emilee Spencer
Published Friday in Marketplace Apps

Marketplace Spotlight: DeepAffects

Hello Atlassian Community! My name is Emilee, and I’m a Product Marketing Manager for the Marketplace team. Starting with this post, I'm kicking off a monthly series of Spotlights to highlight Ma...

64 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot