What is the best way to have two sprint teams working off the same backlog?

I set up the same filter because I they really are working on the same projects, however I didn't expect the velocity or other reports to share info from both teams. Is this the best way to set up a new board or should I be doing something differently?

2 answers

1 accepted

0 vote

You could try using Parallel Sprints as well.

Hope this helps.

Both were good suggestions. The parallel sprints was exactly what I needed and had trouble finding. Thanks again to both of you.

You could use a different filter on each board, which only includes issues assigned to team members + all unassigned issues (for sprint planning). That way, the reports should give details as expected.

See https://answers.atlassian.com/questions/310780/how-to-manage-more-scrum-teams-for-one-backlog

Thanks for the suggestion. I'll try that out and see how it works.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,256 views 10 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you