What is the best way to have two sprint teams working off the same backlog?

I set up the same filter because I they really are working on the same projects, however I didn't expect the velocity or other reports to share info from both teams. Is this the best way to set up a new board or should I be doing something differently?

2 answers

1 accepted

0 votes
Accepted answer

You could try using Parallel Sprints as well.

Hope this helps.

Both were good suggestions. The parallel sprints was exactly what I needed and had trouble finding. Thanks again to both of you.

You could use a different filter on each board, which only includes issues assigned to team members + all unassigned issues (for sprint planning). That way, the reports should give details as expected.

See https://answers.atlassian.com/questions/310780/how-to-manage-more-scrum-teams-for-one-backlog

Thanks for the suggestion. I'll try that out and see how it works.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Monday in Confluence

Organizing your space just got easier - Page Tree Drag & Drop is here

Hi Community! I’m Elaine, Confluence Product Manager. You may have read my earlier post about page tree in space navigation sidebar. I'm excited to share another improvement that helps you organize ...

138 views 3 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you