It seems that Atlassian didn't document what happens when you remove an Agile board.
Are the Agile Boards only some kind of views that do not keep issue related data by themselves? ... meaning that is safe to remove them and to recreate if needed?
This concerns espacially the relationship between sprints and agile boards.
Hi Sorin,
The boards are just a graphic representation of the filters attached to such board. Let's say you remove Board 1 and create Board 2 with the same filter that Board 1 had. Your issues/epics/sprints should all be there. Everything that the filter brings up will be shown in the board.
Cheers!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.