What happens to unfinished issues at end of Scrum sprint?

I'm just getting started with JIRA Software.

Suppose I start a new Sprint (using Scrum) and assign some issues to it. Suppose we get to the end of the sprint and an issue is unfinished. What happens to that issue then?

Furthermore, we want to keep an eye on how long issues take. We have measured them in Sprints. So if an issue is unfinished at the end of a sprint it may end up taking 2 sprints. What is the proper way of measuring issue duration?

2 answers

1 accepted

0 votes
Accepted answer
Thomas Schlegel Community Champion Feb 15, 2016

Hi David,

if you close a sprint with open issues, they are sent back to the top of your backlog. You will get an information about that when closing the sprint.

Thomas

Hi David,

It's true that they're moved back to the top of your backlog, but more specifically, JIRA will consider the next sprint as the top of your backlog (if you've created the next sprint prior to completing the current sprint) and it will put them in there.

Jim

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Wednesday in Jira

Make your Atlassian Cloud products more secure: our NEW admin security guide

Hey admins! I’m Dave, Principal Product Manager here at Atlassian working on our cloud platform and security products. Cloud security is a moving target. As you adopt more products, employees consta...

124 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you