A question related to Advanced Roadmaps:
What happens to existing links between issues if we introduce a new hierarchy level in between?
For example, suppose the current hierarchy configured is Initiatives -> Epics -> Story, 

Epics and Initiatives are linked using the Parent link.


Now, if we introduce a new hierarchy level "Feature" in between Initiatives and Epics, the hierarchy will be
Initiatives -> Features -> Epics -> Story.

Now, what happens to the existing links between Epics and Initiatives?

1 answer

0 votes
Mark Segall
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 10, 2022

Hi @Deepanshu Natani - The links will remain.  It's not like making a workflow change where Jira performs an exhaustive review of all existing issues and adjusts accordingly.  Instead, it's a simple config change. From there you would go into all of your epics and relink them accordingly.