A question related to Advanced Roadmaps:
What happens to existing links between issues if we introduce a new hierarchy level in between?
For example, suppose the current hierarchy configured is Initiatives -> Epics -> Story,
Epics and Initiatives are linked using the Parent link.
Now, if we introduce a new hierarchy level "Feature" in between Initiatives and Epics, the hierarchy will be
Initiatives -> Features -> Epics -> Story.
Now, what happens to the existing links between Epics and Initiatives?
Hi @Deepanshu Natani - The links will remain. It's not like making a workflow change where Jira performs an exhaustive review of all existing issues and adjusts accordingly. Instead, it's a simple config change. From there you would go into all of your epics and relink them accordingly.