What credits the story points to the report?

Here is the situation I need ot solve,

my project's workflow is set up (by the sysadmin?) to credit the story points when the ticket gets closed (which includes QA steps, which are not working concurrently, due to various issues). I'd like to credit the story points when the story is resolved. Is that possible? What needs to change for my projects?

P.S.: I understand that it is not Agile to do QA in bulk and with time delay, but I have no choice and still want to measure the velocity of development in story points.

1 answer

If something is done via a workflow step on issue close, then it should be able to be moved to the workflow step of issue resolved by your sysadmin.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

2,079 views 14 13
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you