View commitment on Velocity chart?

Moria February 23, 2021

Hi there!
On some projects, I don't see the "commitment" grey bar on the chart, although I have added story points.

Where and what should I add to a story point in order for jira to collect that "commitment" info and reflect it in the velocity chart?

Thanks :)

1 answer

0 votes
Moria February 23, 2021

I have figured this out. 
Story points must be added BEFORE sprint starts :)