Hi, In my Gantt tracker, I want to see what the expected finish date is, based on auto scheduling of tasks (based on estimated time and dependencies). I checked multiple fields - due date, end date, finish date, but none of them show the information. What field should I use for this?
See image below, where I tried using due date, but seems to work only when I actually add a due date value in the due date field (manual entry, not automatically calculated).
Hello Namit!
This is Alexey from ALM Works!
The field you're looking for is called Gantt Finish Date:
ps: if there is no such field, you'll need to upgrade your app to the recent version.
Best regards,
Alexey
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.