I found something curious in my version report, while I don't know how to fix it.
I have a version, which is in development since June 2016. Just recently, I've transferred some of the stories from this version to another one. Since then, the predicted, optimistic and pessimistic release dates are equal to each other, while the lightblue offset states different dates. In addition, the releasedate and predicted date are out of the diagram.
How to fix this?
Hi Zethof,
I have seen this kind of problem before in regards to this Agile Report. It appears that this might actually be a bug in regards to way Jira is calculating estimated number of days remaining to complete this release. There is an existing bug on this problem in https://jira.atlassian.com/browse/JSWSERVER-13729
It seems that the methods used to calculate those dates are not correctly taking into account non-working days as set within the options of that board.
In the meantime, there is a possible work-around of adjusting the working days on that board to use all days.
Work-around:
My only concern with this work-around would be the other reports and board aspects that depend on that working days for calculations and how they would change by adjusting this. I understand this work-around likely isn't ideal. However I would recommend watching and voting on that issue to keep up on updates that might resolve this in the long term.
Regards,
Andy
This work around worked for some while now., However, even with all days set to working days, the problem has now returned.
Is there something i can do? Do you need any data to see what's happening?