Using SP and time in one backlog

Thorsten Seidel Feb 20, 2014

Hello,

is it possible to use story points for the userstories and hours or days for the tasks? I would like to use the storypoints for the forecast and the time for the individual tasks.

1 answer

1 accepted

0 votes
Answer accepted
Geert Graat Mar 03, 2014

Hi Thorsten,

We use story points as estimation statistic and have enabled time tracking as well. This allows you to plan sprints in story points and measure your velocity, as well as keep track of the hours estimated for the tasks within a sprint.

Regards,

Geert

Suggest an answer

Log in or Sign up to answer
This widget could not be displayed.
This widget could not be displayed.
Community showcase
Published in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

1,368 views 1 17
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you