Using SP and time in one backlog

Thorsten Seidel February 20, 2014

Hello,

is it possible to use story points for the userstories and hours or days for the tasks? I would like to use the storypoints for the forecast and the time for the individual tasks.

1 answer

1 accepted

0 votes
Answer accepted
Geert Graat
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 3, 2014

Hi Thorsten,

We use story points as estimation statistic and have enabled time tracking as well. This allows you to plan sprints in story points and measure your velocity, as well as keep track of the hours estimated for the tasks within a sprint.

Regards,

Geert