Hello,
We've had this issue happen repeatedly.
We work with 4 columns: "to do", "in progress", "in review", "Done".
The dev team continually moves forward the User Story's without having worked on all of the sub tasks that are still pending.
I am trying to find a way to automate this process by requesting the following:
Has anyone encountered this before? Can it be automated in Jira; maybe even reduced to a simpler automation task?
Cheers
You can achieve this using a sub-task blocking condition in your workflow conditions section see below:
You can then set what status the sub-task must be in for the user to be able to move to the next status see:
I have the add-on scriptrunner installed on my instance and though I doubt it provides this feature, it would be good to check if you have the same condition I highlighted in the first image.
Cheers.
Hello Ismael,
Thank you for your prompt reply.
Very useful, and I can now add in the "sub task blocking condition".
Cheers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This morning, Atlassian announced the acquisition of ThinkTilt , the maker of ProForma, a no-code/low code form builder with 700+ customers worldwide. ThinkTilt helps IT empower any team in their or...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.