Unrelease on Version?

Sandro Gakhokidze March 22, 2012

hello, I clicked release on sprint version in Greenhopper Agile Planning Board.

I'm not sure I like how done tasks just dissapeared, is there way to unrelease sprint version?

or say some other easy windows to view those done tasks I havenot found?

thanks in advance.

1 answer

0 votes
Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 22, 2012

Go to the project, Administer Project, Versions, Unrelease the required Sprint.

The issues that are in released versions won't appear in Version view of Planning Board. But of course it will come in the "Project Overview" provided the filter that you have set for the context includes this.