Under Time Tracking, we are are looking to change Day from 8 hours to 7.6

Barry Marelli August 31, 2014

Hi all,

As part of an internal review, under Time Tracking we are looking to change the "Day" value from 8 hours to 7.6 hours.

Before we proceed with this change, what impact will this have on all previously logged time?

There is a concern that if we make the change, it will interfer with all existing tickets, leading to confusion around reporting.

Any help would be greatly appreciated,

Cheers,

Barry

1 answer

1 vote
Jose M.
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 31, 2014

Should have no impact, since as far as I know Jira uses minutes for the calculation in connection to the current used settings in the time tracking configuration. But your former entries will be adapted, because a 5 day week has no longer 40 hours but 38 hours. So an existing time estimation of 1w will then be 1w and 2h.

Paul Greig
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 1, 2014

Hi Barry & Jose,

Just want to confirm the above behaviour in OnDemand is correct. An issue previously estimated as 1w will adjust to 1w2h upon changing the 'The number of working hours per day' to 7.6.

Cheers,
Paul