Under Time Tracking, we are are looking to change Day from 8 hours to 7.6

Hi all,

As part of an internal review, under Time Tracking we are looking to change the "Day" value from 8 hours to 7.6 hours.

Before we proceed with this change, what impact will this have on all previously logged time?

There is a concern that if we make the change, it will interfer with all existing tickets, leading to confusion around reporting.

Any help would be greatly appreciated,

Cheers,

Barry

1 answer

This widget could not be displayed.

Should have no impact, since as far as I know Jira uses minutes for the calculation in connection to the current used settings in the time tracking configuration. But your former entries will be adapted, because a 5 day week has no longer 40 hours but 38 hours. So an existing time estimation of 1w will then be 1w and 2h.

Paul Greig Atlassian Team Sep 01, 2014

Hi Barry & Jose,

Just want to confirm the above behaviour in OnDemand is correct. An issue previously estimated as 1w will adjust to 1w2h upon changing the 'The number of working hours per day' to 7.6.

Cheers,
Paul

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,489 views 10 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you