Two burndown charts for single active sprint?

Prabhu Chilukuri October 21, 2021

Hi All,

Is there a way to get two burndown charts for single active sprint?

 

Burn Down charts 1. for Story Points & 2. For QA Effort(Custom field).

 

Thanks,

2 answers

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 21, 2021

Hi @Prabhu Chilukuri 

What problem are you trying to solve by charting the information about your custom field, QA Effort?

It seems your team is trying to use the Scrum framework, as you note sprints.  So wouldn't the work for "QA Effort" be part of delivering any story/task to completion for the sprint?  Perhaps consider what is in the team's definition of done for story/task work.

Thanks, and kind regards,
Bill

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 21, 2021

Technically, because one (or both) of them would not be a burn-down chart.

Your board has a setting of "what to estimate on" and that one single value is what you burn down on.  You do not burn down on another estimate.

However, you can get Jira to show you these charts.  If you change the estimation setting on the board, you'll get a chart based on that.  This will, of course, make a complete nonsense of your sprint and not be an actual burn-down, but it will get you the chart.

The other option is to create an identical copy of the board, and change the estimation on that.  Again it'll give you a chart that is nonsense and not a burn-down, but it's better than flipping the original boards setting - you can keep this board hidden to stop people making a mess of the sprint while you're generating the chart.

Suggest an answer