Reading up on time management it says that time tracking on an Agile project can be turned on by configuring the Board. I simply cannot find how to do that - which could be because I am being blind to something obvious. Time tracking on all projects (agile or work management) is vital for me to be able to plan overall workloads and actually track who has been working where.

3 answers

Hello @John Pinnell 

Welcome to the community.

Are you working with a Team Managed project or a Company Managed project? It will say at the bottom of the navigation pane on the left.

What document are you referencing for instructions about enabling time tracking?

There are two elements to time tracking. One is the ability to log time. The other is the use of time for estimation in an agile board.

This document addresses the ability to log time, for a Company Managed project:

https://support.atlassian.com/jira-cloud-administration/docs/configure-time-tracking

This document addressed the use of time for estimation in an agile board for a Company Managed project.

https://support.atlassian.com/jira-software-cloud/docs/configure-estimation-and-tracking

The information provided by @KAGITHALA BABU ANVESH is for Company Managed projects.

 

 

For a Team Managed project you enable the ability to log time by ensuring the Time Tracking field is added to the issues. Do that by selecting Project Settings > Issue Types. For each issue type, ensure the Time Tracking field in included.

https://confluence.atlassian.com/jirasoftwarecloud/customize-an-issue-s-fields-in-team-managed-projects-951392551.html

To use Time for estimation for the board of a Team Managed project select Project Settings > Features, and ensure that the Estimation feature is on and the Time (vs. Story Points) option is selected.

1 vote
Fabian Lim Community Leader Dec 28, 2021

Hi @John Pinnell

Welcome to the community!

Did you follow these instructions: https://support.atlassian.com/jira-software-cloud/docs/log-time-on-an-issue/

Regards

1 vote

Hello @John Pinnell ,

 

Please check the below settings.

1. Time Tracking must be enabled 

If you are jira admin --> go to Settings --> issues --> Under "Issue Features" --> Time Tracking check the above is enabled or not

 

2. Go to the required project settings --> Permissions --> "Work on issues"

 For the users you wish to be able to log work on issues, ensure that they have the Work On Issues permission in project permissions.

 

3. Go to the project --> open Board --> Board settings -->  check the below settings

image.png

 

please check all the above.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira Software

👋 Looking for 15-20 volunteers to test Atlassian training content

Hi everyone! Are you interested in beta testing Atlassian University’s newest (unreleased!) training course? We’re looking for 15-20 volunteers to test our newest training course, Basic reporting...

577 views 21 25
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you