Time tracking on a task only if is "In Progress"

REDA EL HAIDAWI EL IDRISSI September 14, 2022

Hello Community,

Please i need to edit Jira, so my co workers can time track on a task only if is "in progress".

I want to prohibit the time tracking if the task is not in the "In Progress" state.

If someone know how to do it please.

Thank You.

1 answer

1 accepted

3 votes
Answer accepted
Fabio Racobaldo _Herzum_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 14, 2022

Hi @REDA EL HAIDAWI EL IDRISSI ,

welcome to the Atlassian community!

In order to do that you need to setup workflow properties (https://support.atlassian.com/jira-cloud-administration/docs/use-workflow-properties/).

In particular you need to add the following property key : jira.permission.work.denied value : leave empty for each status different from In Progress in your workflow.

This is the trick.

Hope this helps,

Fabio

REDA EL HAIDAWI EL IDRISSI September 14, 2022

Thank you so much @Fabio Racobaldo _Herzum_ for your help, it worked well for me.

Fabio Racobaldo _Herzum_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 14, 2022

you're welcome @REDA EL HAIDAWI EL IDRISSI 