Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,466,098
Community Members
 
Community Events
176
Community Groups

Tickets still "opened" at the end of the sprint even if they are flagged "achieved/closed"

image.png

1 answer

1 accepted

2 votes
Answer accepted
Trudy Claspill Community Leader Nov 28, 2022

Hello @Delphine FALCOZ 

Welcome to the community.

The issue has to be in a status that is mapped to the column farthest to the right on the board in order for it to be considered Complete when you complete the sprint.

It does not matter what the status of the issue is. It only matters that the status is mapped to the right-most column.

Also, if the issue has sub-tasks, all the sub-tasks must also be in a status mapped to the right-most column.

Hello @Trudy Claspill 

 

Thanks for your fast answer.
You're right, you fixed my issue !

Thanks a lot :)