Tickets in Done column not disappearing when sprint ends

Chun Yee Lau August 22, 2022

I am currently using a team-managed project on the Cloud to run sprints. The tickets in the done column are not disappearing from the sprint once the sprint ends. How do I make the tickets disappearing once they are done and we start a new sprint?

Thanks. 

1 answer

1 vote
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 22, 2022

Hi Chun,

Is the Done column that very last column on the board (far right)? That's the only way that the sprint will consider them completed. 

Chun Yee Lau August 27, 2022

Hi John, my Done column was not the last one on the sprint board. I moved it to the last. Hopefully this will work when the sprint ends. Thanks for your help!

Like John Funk likes this

Suggest an answer

Log in or Sign up to answer