The same issue is displayed in two active sprints during the planning in two teams

Alex Kiselev _Itransition_ December 15, 2013

Following situations appeared twice.

The same time 2 different teams create 2 separate sprints:

Team A creates Sprint A, Team B creates Sprint B.

Team A includes issue I into Sprint A from backlog, the same time Team B see that issue I is in sprint B.

Thanks in advance.

3 answers

1 accepted

0 votes
Answer accepted
Alex Kiselev _Itransition_ March 19, 2014

Teams schedules were arranged the way that prevent appearing the problem

0 votes
Alex Kiselev _Itransition_ December 16, 2013

Just to clarify:

the problem is "Team B see that issue I is in sprint B" (issue is in wrong sprint) - but nobody included issue in sprint B

0 votes
Mauro Badii
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 16, 2013

Hi Alex,

This previous question might help you understand the situation: One issue in two backlogs, what happens if sprint created

Looks like you can have them in the backlog but not on a started or planned sprint.

Cheers,
Mauro

Suggest an answer

Log in or Sign up to answer