Sum up timetracking original estimate from tasks up to epic

Jung Kim May 6, 2021

Looking for automation to sum up all the original estimate under epic (tasks).

 

Trying to setup automation but the action part keeps failing.

 

{{#=}}{{issue.timetracking.originalEstimateSeconds.sum}}/60{{/}}

1 answer

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 6, 2021

Here is an article about summing up different time fields from sub-tasks to parent stories, and it also includes some information in the comments about summing up time from child issues to Epics.

https://community.atlassian.com/t5/Automation-articles/How-to-sum-up-logged-hours-using-automation-in-Jira-Cloud/ba-p/1409115

I haven't gone through all of it, but it might contain the answer to your question

Jung Kim May 6, 2021

thank you!