Sum subtasks in the board agile

Hi

I have one task in the backlog. This task has two subtask with 5 days with time estimate. When I select this task to the sprint the time estimate is blank?.

Any idea?.

My board configuration is Estimantion Stastic = Origina Estimate

regards

1 answer

1 vote
Anna Cardino Atlassian Team May 21, 2014

Hello Cesar,

This seems to be an expected behaviour as stated inhttp://blogs.atlassian.com/2012/09/agile-qa-greenhopper-time-estimates-with-sub-tasks/.

However, I came across to this ticket describing the functionality that you need; GHS-9167.

Kindly to the following on the ticket to increase it's popularity and get more attention to Atlassian developers:

* Vote, so that it will receive more attention

* Watch it, so that you will receive any and all updates

* Comment, and give your opinion on the matter

Hope it helps.
Regards,
Monique

Suggest an answer

Log in or Join to answer
Community showcase
Emilee Spencer
Published 3 hours ago in Marketplace Apps

Marketplace Spotlight: DeepAffects

Hello Atlassian Community! My name is Emilee, and I’m a Product Marketing Manager for the Marketplace team. Starting with this post, I'm kicking off a monthly series of Spotlights to highlight Ma...

22 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot