If I create a Story and then add sub-tasks to it, this is what I get:
How can I get the Original Time Estimate to be the sum of the Story's sub-tasks estimations, automatically?
Thanks.
Hi Franco,
This is impossible in JIRA Agile. If you notice, only standard (parent) issues are displayed in Plan mode while sub-tasks are not. The idea behind is to take into account the original estimate of parent issues only. However, remaining estimate of sub-tasks will be cumulated into parent's remaining estimate, which will be used for time tracking in Work mode, where the sub-tasks are visible. So basically:
You can read more about this here.
Cheers.