Story original time estimate

If I create a Story and then add sub-tasks to it, this is what I get:

How can I get the Original Time Estimate to be the sum of the Story's sub-tasks estimations, automatically?

Thanks.

1 answer

1 accepted

0 vote
Andy Nguyen Atlassian Team May 11, 2014

Hi Franco,

This is impossible in JIRA Agile. If you notice, only standard (parent) issues are displayed in Plan mode while sub-tasks are not. The idea behind is to take into account the original estimate of parent issues only. However, remaining estimate of sub-tasks will be cumulated into parent's remaining estimate, which will be used for time tracking in Work mode, where the sub-tasks are visible. So basically:

  • Plan mode is for planning original estimate of parent issues
  • Work mode is for tracking remaining estimate of both parent and sub-tasks

You can read more about this here.

Cheers.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,232 views 10 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you