Stories with Sub Tasks

Hi ,

I have created a story with 3 sub tasks . I entered time estimates in sub tasks , logged work and moved them in different status as per my workflow . All the subtasks are moved into Done travelling from To do , in progress , in test and finally to done but main story item is still in To do . How can I move that parent issue to done .

Thanks

1 answer

1 accepted

This widget could not be displayed.

You can go into the story and 'resolve'/'close' it and that will put it in the done category. Unless you have stories configured as swimlanes, then when you move to the next sprint it shouldn't be included in that one.

Oh yes , it worked , i have changed to no swimlanes...but just in case If i want that swimlanes do stay there and at the same time when all the subtasks are closed , main story is also closed , can you please shed a bit of light on this too ?

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,449 views 10 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you