I recently moved all issues from a team-managed project to a company-managed project (following the step by step instructions). The 'source' team-managed project had a roadmap. I would have thought that the roadmap would have moved with the issues. I did not create a roadmap on the 'target' company-managed project prior to moving the issues.

Is there a way to indicate that I want to move the roadmap during the issue move?

1 answer

1 accepted

1 vote
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 6, 2022

Hello @Mike Morris 

No, unfortunately you cannot move the roadmap associated with a Team Managed project to a Company Managed project (or vice versa). There are architectural differences in the project types that make this incapable of being supported.

Mike Morris June 6, 2022

Thanks for responding and letting me know.