It seems that the sprint health gadget is not working properly for a Jira board in my project. It´s showing 0% although there have been scope changes in the last days (and we can see them by clicking on the 0%).
The Board filter query is as below:
"project = DS3 AND type in (Epic, Story, Task, Bug) AND ("Digital Stream Topic Cluster" = DS3_Operational_QM OR issuekey in (DS3-634, DS3-639, DS3-644, DS3-649)) ORDER BY Rank ASC"
Could you please help me here?
I had the same problem until I went to the board configuration, "Estimation" area and made sure the estimation statistic is set to Story Point and I changed Time Tracking to be "None" when it was "Remaining Estimate and Time Spent".