Sprint Report - shows resolved issues as non completed

francis
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
August 18, 2013

We are running latest JIRA (6.0.6) and Agile plugin (6.2.5.1).
On Aug 19 (today) we closed a sprint which was running from July 21 until August 9.

On the sprint report we see a list of issues as 'non completed', although the resolution has been set on August 8 and the status is set to 'closed'.

These issues are not appearing on the planning board.

Why are these issues considered as 'non completed' in the sprint report ?


2 answers

1 accepted

2 votes
Answer accepted
francis
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
August 18, 2013

Found the reason.

The status 'close' was not mapped - this is interpreted by the agile plugin as if the issue is not completed, while in fact it is.

1 vote
Malo March 12, 2015

Same issue there while the 'close' status is mapped. My problem was that the 'close' column was not the last !

Kadar Khan June 16, 2017

Thanks, I checked many tickets as a Bug on this. Finally did ur trick by moving Close Column to Last.

Suggest an answer

Log in or Sign up to answer