I am using "Remaining Time Estimate" as the chosen metric on my burndown report, so I get a red line which burns down the hours estimated for tasks in the sprint. I also get the green line, which is supposed to report the time spent.
My users are entering time as we would expect, updating remaining hours and zero'ing out (sub)tasks that are completed ahead of schedule. The red line reflects exactly what I would expect.
I can't figure out the logic behind the green line though. From what I can see it updates on some sort of schedule, usually at 7:00PM(00:00 GMT), but not always. For instance in the image I'm attaching, on 4/17 it jumps up at 9:00AM.
I've also noticed sometimes it doesn't take work logged into account even when it does jump up.
My questions are:
Catch up with Atlassian Product Managers in our 2020 Demo Den round-up! From Advanced Roadmaps to Code in Jira to Next-Gen Workflows, check out the videos below to help up-level your work in the new ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events