The Roadmap in my project (as well as other projects I tried) is moving all Epic bars back by 1 day every time I refresh.
Seems when you move the bar in the Roadmap, the date being saved in the 'Start date' field is one day off.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm seeing the same behavior and don't know why. I turned off all my automations and it's still happening. I do not have any 3rd-party apps installed. Please advise Atlassian team! Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It's a timezone bug in JIRA - they've logged this item to handle: https://jira.atlassian.com/browse/JSWCLOUD-23125