Removing "Schedule Issue" permission still allows users to add issue to sprint from planning board.

Nimitt Desai November 7, 2013

I have removed "Schedule Issue" permission for a particular user group. When they try to add issue to sprint from backlog to sprint from planning board, error msg is displayed.

This is expected but issue is moved to sprint anyways.

3 answers

1 accepted

2 votes
Answer accepted
petry
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 12, 2013

This is a bug in JIRA Agile and it's being tracked here: https://jira.atlassian.com/browse/GHS-8966

1 vote
PedroA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 8, 2013

Hi Nimitt, how you doing? =)

Only users with Project Administrator permissions (as per Project Permissions) can add/drag issues into sprints. If you would like to prevent users from doing this, restrict their Project Administrator permissions. See more of this subject here:

* What are the permissions used in Agile Boards

Cheers,
Pedro.

0 votes
Nimitt Desai November 11, 2013

Interestingly issue can only be added to in progress sprint. Can't be added to sprint that has not yet started.

Suggest an answer