Should the release move 'done' cards of the board?  I created a release with a 2 month date range and nothing was moved off done coloumn?

2 answers

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 26, 2021

For a Team Managed project Kanban board, the Done column displays issues resolved in the last 14 days. Based on my experimentation, it does not appear to matter if the issues are in a Released version or not.

Martin Hemi May 26, 2021

Hi Trudy. 

Will the cards drop off the done column after 14 days?

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 26, 2021
Martin Hemi May 26, 2021

excellent thank you