After I added the Sprint field to my roadmap, I noticed a message displayed saying Sprint not currently in this plan. While the sprint isn't included in this plan, its appearing because its assigned to issues in this plan. See screenshot. I don't understand this message. When I created the plan, I included the issues for the entire project. So why am I getting this message that the sprint isn't in the plan. How do I include the sprints in a roadmap plan?
Hi @John Bacon , the mentioned sprint is not part of the plan because it's not in scope of your plan.
You'll need to add it either by adding the project to the issue source of the plan, updating the JQL of your filter or updating the filter of your board which was added to the issue source of your plan.