Can I reorder the way the sprints appear in the backlog?

brenda weisz blanchetta
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 6, 2018

Is it possible to adjust the way the sprints appear in the backlog?

At the moment it is shown in order of creation, not even on the startdate of the sprint.

I would like to order it on date or importance (when a start date is not created yet)

1 answer

1 accepted

1 vote
Answer accepted
Pilar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 2, 2015

So, when I go to Reports from a given board, will I get data from what was filtered to be visible on that board?  

Pilar: Yes, you get reports on the information that is available on that board (filtered using the board filter)

I'm trying to determine how to best run multiple teams through a sprint, maintaining the ability to report against subsets of those teams, and a view into all teams progress in aggregate.

Pilar: Your approach is the best. Have multiple boards for sub-teams reporting and also have a parent board for showing aggregate of the entire project.

Another alternative approach to consider is to run parallel sprints (on the same board) for each sub-team.

But here you lose the ability to get the aggregate picture.

Pilar


Matthew Penfield
September 3, 2015

great, thanks so much for clarifying