Hi,
With my team, we want to use a kanban board to handle backlog refinement, and then we want to use a Scrum backlog, board, and sprint for development.
I set up a simple workflow (something like: open -> refinement -> ready for sprint -> to do -> in progress -> finished)
The Kanban board shows the first steps and we want the issues to fall into the sprint backlog at the “Ready for Sprint” step.
The sprint board filter has “Ready to sprint” and up.
We can see the issues in the sprint backlog if the “Ready for sprint” column is configured in the sprint table, but we don't want to display this column in sprint board.
I've tested the solution of this thread without success:
What did I miss?
Thanks a lot for your help.
For a Company Managed project Scrum board, the first column of the board is the "starting" status of the Sprint by design. The design is such that the first status represents issues in the backlog and issues in a Sprint where work on those issues has not yet started. Typically more work is added to a sprint than can be started all at once, so it makes sense to have a "work not started yet" status for the issues in the sprint. As the work starts on an issue, the issue is then transitioned to the "in progress" status.
If you don't include that status on the board, then the issues will not display in the scrum backlog either. That is also by design.
In my opinion, you should collapse the"ready to sprint" and "to do" statuses into one status.
By design, you can't have a status in a Scrum board that is only for displaying issues in the backlog. The column also has to be mapped to a column of the board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @adrien.bacarisse ,
That is tricky. I am thinking of a solution, but haven't tested it.
Add a post-function on refinement -> ready for sprint transition. (let us say CF1 will be updated to "Ready")
Now modify the scrum board's filter query to include this field
project=ABC and CF1='Ready'
The above query may get all issues from the project that has a value for CF1 ( which is provided during the transition). You can add columns to the board(excluding ready for sprint and they will be under unmapped issues). Backlog must contain all issues with CF1='Ready' value though.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.