It is not 100% clear why some requirements don’t appear in the master portfolio view. I would like to know how this page behaves for the following three scenarios:
1) Feature A is inside Sprint 1 and is tagged with Release 1.0.
Feature A is marked as DONE but Sprint 1 is not completed yet, should Feature A appear in the scope of Release 1.0?
2) Feature B is inside Sprint 1 and is tagged with Release 1.0
Feature B is marked as DONE and Sprint 1 IS completed. should Feature B appear in the scope of Release 1.0?
3) Feature C is inside Sprint 1 and is tagged with Release 1.0
Feature C is NOT marked as DONE but Sprint 1 IS completed. Should appear ins scope Release 1.0?
Hello Jorge,
In all three scenarios issue should appear in scope if it was completed within the period set by "Completion date" filter (last 30 days by default). If an issue was completed earlier it will not appear in scope in all three scenarios.
----
Portfolio for Jira Server team